October 5 - Kitchen Counter Tops & Septic Tank
October 6 - Final Trim Begun and Septic Tank Finished
October 7 - Trim, Plumbing, Registers, Garage Doors, etc.
October 8 - Electricity Connected to the house - no temporary box on the pole anymore.
October 13 - Appliances, Hardware, Mirrors, Shower
October 15 -Sidewalk, Driveway & Patio Forms
October 18 - Outside Concrete Done
October 19 - Front Door minus glass - Security System - Screened in Porch - Driveway Started
October 20 - Screened Porch Done - AC Installed - Wood Stove - Driveway Progressing
October 25
Shower Seat, Tile Backsplash, Pedestal Sink, First Ceiling Fan and ----
the air was cooooool inside, the AC works!!